130203 CCT-03

Wagon Group volunteer Philip has spent two successive working sessions cleaning up and priming the structural steelwork. By the end of the first day, he had cleaned up the rust and primed up to the central doors on the south side.

 

DSCF3366 - CCT 6Feb12

A week later, he cleaned and primed the remaining half…

 

DSCF3365 - CCT 6Feb12

…and made a start on the north side. He estimates another two working sessions will be required to complete preparation of the bodyside steelwork. (All photos courtesy of Philip Halstead).